Determine the estimated cost of the work performed


Question:

Determine the estimated cost of the work performed each week given the tasks-with their associated costs and schedules-shown in the following table. When a task spans more than one week, the costs should be divided equally among the weeks.


WEEK


T ASK

C OST ($)

S TART


FINISH

Excavation

2,200

1


1

Footings and Foundation

19,600

2


3

Waterproofing

900

3


3

Backfill and Under Slab Gravel

2,000

4


4

Slab on Grade

22,300

4


4

Masonry

54,000

5


7

Structural Steel

2,400

8


8

Joist and Deck

11,900

8


8

Hollow Metal Doors and Hardware

2,100

9


9

Overhead Doors

10,100

9


9

Skylights

5,800

9


9

Roof Insulation

5,600

10


10

Membrane Roofing

13,000

10


10

Heating

15,600

11


11

Electrical

29,800

11


12

Cleanup

1,000

12


12

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Determine the estimated cost of the work performed
Reference No:- TGS02051386

Expected delivery within 24 Hours