Problem
Japan Company produces lamps that require 3 standard hours per unit at an hourly rate of $15.70 per hour. Production of 6,900 units required 20,290 hours at an hourly rate of $16.20 per hour.
(a) Determine the direct labor rate variance.
(b) Determine the direct labor time variance.
(c) Determine the cost variance.