Determine the critical path by activities and duration.
Activity Duration (Wks) Preceded by
A 5 -
B 4 -
C 2 A, B
D 2 C
E 7 D
F 3 E
G 1 F
H 2 G
I 4 G
J 1 H, I
Determine the critical path above specified activities and find out what the elapsed time of the project would be? Determine no. weeks that activity H over run by without affecting the elapsed time of the project?