The following information is known about a project.
Activity Activity Time (days) Immediate Predecessor(s)
A 7 -
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E
Draw the network diagram for this project, determine the critical path and project duration and calculate the slack for each activity.