Problem:
Using the activity matrix information and diagram, how would I determine:
- the crash cost per day for each activity
- which activities I would have to crash in order to meet a 12 day deadline at minimum
cost
- how much more would it cost to crash the project
Activity Normal Time Crash Time Normal Cost Crash Cost
A 5 3 $300 $600
B 3 2 $250 $450
C 6 4 $400 $500
D 5 3 $150 $400