Exercise- Allocating Manufacturing Overhead to Jobs
Webber Fabricating estimated the following annual costs.
Expected annual direct labor cost $ 625,000
Expected machine hours 20,000
Expected material cost for the year $ 800,000
Expected manufacturing overhead $ 1,000,000
Required - Determine the cost of the following job (number 253) using each of the four overhead allocation rates.
Job 253
Direct materials $3,000
Direct Labor (150hrs @$12/hr) $1,800
Machine hours used 150