Determine the cost of reducing the project completion date


A) Determine the cost of reducing the project completion date by 4 months from the normal time.

B) What is the maximum time that can be crashed?  How much would cost increase - you must indicate which activities are being crashed, by how many days and at what cost?

Activity Preceded by Normal time (months) Crash Time (months) Normal Cost Crash Cost

1 - 7 5 2000 2600

2 1 12 6 1000 1300

3 1 7 5 3000 3500

4 3 6 4 2000 2400

5 2,4 9 8 8800 9100

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine the cost of reducing the project completion date
Reference No:- TGS02163734

Expected delivery within 24 Hours