If there is an incentive of $ 500 per week of early opening for the SIBC ' s satellite outpatient center in diagram, determine the compression activities and compressed completion time.
Exercise :
Given the diagram shown in Figure EX 13.2, with duration times for activities A through L:
a. Identify the paths and path duration times.
b. Determine the critical path.