Determine the capacity utilization for labor and machine


A company that manufactures paving material for driveways and parking lots expects the following demand for its product for the next four weeks:

Week number

1

2

3

4

Material (tons)

40

80

60

70

The company's labor and machine standards and available capacities are as follows:

 

Labor

Machine

Production standard (hours per ton)

 

4

 

3

Weekly production capacity (hours)

 

300

 

200

a. Determine the capacity utilization for labor and machine for each of the four weeks.

b. In which weeks do you foresee a problem? What options would you suggest to resolve any problems? What costs are relevant in making a decision on choosing an option?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine the capacity utilization for labor and machine
Reference No:- TGS01227376

Expected delivery within 24 Hours