As coding manager , you are in charge of a new encoder purchase. This is your first attempt at project management and you want to manage it effectively. You create a Gantt chart to illustrate the project from vendor selection to go live.
Determine the baseline duration of the critical path of the project.
Determine the variance that causes a week's delay.
Determine the variance that put the project back on track.
Give an opinion on whether this was a successful project implementation or not and support your decision.
Evaluate the impact of the document completion task on the overall project.