Activity Cost
|
Activity Base |
Procurement |
$370,000
|
Number of purchase orders |
Scheduling |
250,000
|
Number of production orders |
Materials handling |
500,000
|
Number of moves |
Product development |
730,000
|
Number of engineering changes |
Production |
1,500,000
|
Machine hours |
|
|
Number of Purchase Orders
|
Number
of
Production
Orders
|
Number of Moves
|
Number of Engineering Changes
|
Machine Hours
|
Number of Units
|
Disk drives |
4,000
|
300
|
1,400
|
10
|
2,000
|
2,000
|
Tape drives |
4,000
|
150
|
800
|
10
|
8,000
|
4,000
|
Wire drives |
12,000
|
800
|
4,000
|
25
|
10,000
|
2,500
|
Determine the activity rate per production order for scheduling.