1. Determine the absolute shortest length of time in which the telemedicine project can be completed if none of the activities are crashed.
2. Determine the shortest length of time the project can be finished if activities on the critical path are crashed.
3. Calculate the additional cost resulting from crashing all the activities possible.
4. Explain how you can minimize the additional cost of crashing the project while completing the project in the same amount of time as determined in question 2.