Development of the new deluxe version of the particular software product is being considered. Activities essential for completion of the project are given in the table below along with costs and completion times in weeks:
Activity
|
Direct Costs
|
Cost
per crash
($)
|
Max. Crash Time
(week)
|
Normal
|
Crash
|
Time (week)
|
Cost
($)
|
Time (week)
|
Cost
($)
|
A
|
5
|
500
|
4
|
600
|
100
|
1
|
B
|
10
|
1200
|
6
|
2000
|
200
|
4
|
C
|
13
|
3600
|
11
|
4800
|
600
|
2
|
D
|
3
|
300
|
1
|
600
|
150
|
2
|
E
|
9
|
1000
|
8
|
1400
|
400
|
1
|
F
|
10
|
2400
|
8
|
5400
|
1500
|
2
|
G
|
5
|
700
|
5
|
700
|
0
|
0
|
Paths:
i) A -> C -> F -> G
ii) A -> B -> E -> G
iii) A -> B -> D -> E -> G
i) Determine project expected completion date?
ii) Determine total cost needed for completing the project on normal time?
iii) If you want to decrease time needed to complete the project to only 29 weeks, which activity must be crashed, and how much will the increase total cost? Illustrate Cost Changes and Activities Changed in workings to get answer.