Problem 1:
The Assembly Department of Webster Manufacturing uses a process cost accounting system and a weighted-average cost flow assumption. The department adds materials at the beginning of the process and incurs conversion costs uniformly throughout the process. During July, $190,000 of materials costs and $135,000 in conversion costs were charged to the department. The beginning work in process inventory was $103,000 on July 1, comprised of $80,000 of materials costs and $23,000 of conversion costs.
Other data for the month of July are as follows:
Beginning work in process inventory, 7/1 25,000 units (40% complete for conversion costs)
Units completed and transferred out 70,000 units
Ending work in process inventory, 7/31 30,000 units (30% complete for conversion costs)
Required: Prepare the July production cost report for the assembly department.
Problem 2:
Angara Corporation uses activity-based costing to determine product costs for external financial reports. The company has provided the following data concerning its activity-based costing system:
|
Activity Cost Pools (and Activity Measures)
|
Estimated Overhead Cost
|
|
Machine related (machine-hours)................................
|
$137,600
|
|
Batch setup (setups)....................................................
|
$532,800
|
|
General factory (direct labor-hours)............................
|
$105,300
|
|
|
|
Expected Activity
|
|
Activity Cost Pools
|
Total
|
Product X
|
Product Y
|
|
Machine related..........................................................................
|
8,000
|
1,000
|
7,000
|
|
Batch setup................................................................................
|
8,000
|
3,000
|
5,000
|
|
General factory..........................................................................
|
9,000
|
7,000
|
2,000
|
Required: Determine the amount of overhead to be allocated to each of the two products under activity-based costing.