Determine process velocity


Mop and Broom Manufacturing estimates that it takes 4½ hours for each broom to be produced, from raw materials to final product. An evaluation of the process reveals that the amount of time spent working on the product is 3 hours. Determine process velocity.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Determine process velocity