Determine probabilities of completing given project


Determine critical path and project completion time for given list of activities. Determine probabilities of completing given project in:

i) 11 days or less

ii) 12 days or less

iii) 13 days or more

iv) between 12 and 14 days.

Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration
A - 2 3 9
B - 2 4 4
C A,B 2 4 6
D A,B 2 5 8
E C,D 1 3 10

Request for Solution File

Ask an Expert for Answer!!
Mathematics: Determine probabilities of completing given project
Reference No:- TGS0867528

Expected delivery within 24 Hours