Seven jobs must be scheduled in two operations: A and B. All seven jobs must go through A and B in that sequence A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times:
Job "Process A
Time" "Process B
Time"
1 9 6
2 8 5
3 7 7
4 6 3
5 1 2
6 2 6
7 4 7