Seven jobs must be processed in two operations: A and B. all seven jobs must go through A and B in that sequence - A first, then B.
a. Using the times below, determine the optimal order in which the jobs should be sequenced through the two processes.
b. When does the last job in a sequence leave process B?
Job Process A Time Process B Time
1 9 6
2 8 5
3 7 7
4 6 3
5 1 2
6 2 6
7 4 7