Determine if the following test marketing project at week 6 is in control. If not, what is out of control? If it is in control, are both budget and schedule in control?
Q10 At week 24 of a project to shoot a television commercial, the project manager is worried about her budget since costs have risen to $7,500. Is there a cost overage? If so, how much is it? Is the schedule ahead or behind? Overall, does the project appear to be in control?