Assignment:
Q: Make your own educated guesses as to how long each task below will take. Decide which tasks can be performed concurrently (at the same time) and which tasks are dependent (can only begin when others have been completed).
Make sure your (PERT/CPM) chart displays the critical path.
Here are 5 phases (in bold) and their tasks:
Project Planning and Evaluation
Project Kickoff
Select Interviewers for team
Create interview questions for survey
Meet/Organize Team
Interview college administrators, IT Staff, Faculty Members, and students in formulating student needs, requirements, and preferences
Develop Data Flow Diagrams, Data Dictionaries
Meet with Team to finalzie results
Project Analysis and Scheduling
Determine Hardware, Software, and networking requirements
Analysis required data gathering
Develop insights with users
Scheduling methods with various project implementation
Evaluate cloud vs in house alternatives
Get user acceptance for systems requirement document
Project Design, Testing, and Monitoring
Purchase hardware, software, and networking equipment
Install software and hardware
Configure and test networking
Test hardware and software installations
Write systems requirement documents for systems
Write systems requirement documents for proposed surveys
HTML programming for surveys
HTML Testing for surveys
PHP and MySQL programming for surveys
PHP Testing
MySQL Database Testing
Volume and peak load testing
User system and integration testing
Project Implementation
Receive, install, set up, and configure test hardware and software platform.
Implement System
Project Reporting and Support
Evaluate Performance
Schedule user and developer feedback meeting
Document recommended improvements
Develop and implement system changes and maintain procedures