Question: A company needs to manage a project which consists of the following set of activities.
Activity
|
Days
Required
|
Predecessor
Activities
|
A
|
5
|
-
|
B
|
6
|
--
|
C
|
9
|
B
|
D
|
9
|
A, C
|
E
|
3
|
A
|
F
|
20
|
D, E
|
Draw an AON network.
- Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest Finish time (LF), and Slack for all the activities.
- What is the critical path for the project and how long should it take to complete it?
- Identify each path through the network using activity name (example: A, B etc.) from beginning to end, and its expected length of time.