Determine critical path and project completion time


Determine critical path and project completion time for given list of activities. Determine probabilities of completing project in

i. 13 days or more

ii. 11 days or less

iii. between 12 and 14 days

Activity

Immediate

Predecessor

Optimistic

Duration

Most Probable

Duration

Pessimistic

Duration

A

-

1

3

5

B

-

2

4

6

C

A, B

2

4

5

D

A, B

3

5

7

E

C, D

1

2

10