Determine critical path and project completion time for given list of activities. Determine probabilities of completing project in
i. 13 days or more
ii. 11 days or less
iii. between 12 and 14 days
Activity
|
Immediate
Predecessor
|
Optimistic
Duration
|
Most Probable
Duration
|
Pessimistic
Duration
|
A
|
-
|
1
|
3
|
5
|
B
|
-
|
2
|
4
|
6
|
C
|
A, B
|
2
|
4
|
5
|
D
|
A, B
|
3
|
5
|
7
|
E
|
C, D
|
1
|
2
|
10
|