Response to the following problem:

Express Delivery Company acquired an adjacent lot to construct a new warehouse, paying $80,000 and giving a short-term note for $620,000. Legal fees paid were $1,900, delinquent taxes assumed were $9,000, and fees paid to remove an old building from the land were $6,000. Materials salvaged from the demolition of the building were sold for $1,175. A contractor was paid $800,000 to construct a new warehouse.

Determine the cost of the land to be reported on the balance sheet.

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Determine cost of land to be reported on balance sheet
Reference No:- TGS02120558

Now Priced at $20 (50% Discount)