Problem: Using the data in the table, complete the following
• Draw a network diagram
• Perform the forward and backward pass : determine the ES, EF, LS and LF dates
• Determine and identify the critical path
• What is the duration of the project ? Which activities have a float ?
• Develop a profile of the amounts to be spent per month based on your project schedule
• What is the total project budget at completion
Activity
|
Predecessor
|
Duration
|
Total Cost
|
A
|
-
|
5
|
$5,000
|
B
|
-
|
10
|
10,000
|
C
|
A, B
|
7
|
7,000
|
D
|
C
|
12
|
12,000
|
E
|
D
|
15
|
15,000
|
F
|
D, E
|
12
|
12,000
|
G
|
C, F
|
8
|
8,000
|
I
|
E, G
|
9
|
9,000
|
J
|
I
|
10
|
10,000
|