Assignment:
A machine cell uses 226 pounds of a certain material each day. Material is transported in vats that hold 28 pounds each. Cycle time for the vats is about two hours. The manager has assigned an inefficiency factor of .04 to the cell. The plant operates on an eight-hour day.
How many vats will be used?