Determine a new sausage system with an installed cost


Kolby's Korndogs is looking at a new sausage system with an installed cost of $924,000. This cost will be depreciated straight-line to zero over the project's seven-year life, at the end of which the sausage system can be scrapped for $109,000. The sausage system will save the firm $197,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $55,000.

Required:

If the tax rate is 30 percent and the discount rate is 6 percent, what is the NPV of this project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)