In a time study of a process, the average time to complete a unit was 36.5 minutes, the performance rating of the worker observed in the study was 1.2, and the allowances were 60 minutes per eight-hour shift. What would the labor standard be for the process?
Name six different factors that might be important to a company deciding on a location for a new facility. For each of the factors, explain why it would be important in the location decision.