Describe the differences between level, chase, and mixed production plans. Use the forecast in the table to show the differences by creating a plan of each type. There is no beginning inventory and regular production capacity is 350 units. Overtime costs $10 extra and is limited to 50 units per month. Subcontracting is limited to 100 units per month and costs $15 per unit. Back orders cost $40 per unit and there is a cost of $5 per month to hold a unit in inventory. There is room for only 100 units in inventory.
Month Forecast
January 250
February 300
March 500
April 350