Problem: The beta distribution is used in project management to:
Select one:
a. calculate pessimistic and optimistic activity times.
b. calculate slack on activities not on the critical path.
c. calculate the probability that a project will be completed within its budget.
d. determine which activity should be crashed.
e. none of these