Which of the following best describes a gross material requirements plan? a a schedule that shows total demand for an item, and when it must be ordered from a supplier or when production must be started. b. an intermediate range plan for the scheduling of families of products. c. a chart illustrating whether capacity has been exceeded d. a table that corrects scheduled quantities for inventory on hand. e. a schedule showing which products are to be manufactured and in what quantities.