Define predecessor, successor, and parallel activities. Give a real world example of each. -
In the context of critical chain project management, what is resource contention?
Define the following and give a real world example of each (other than the ones described in the text book): Finish-to-Start; Start-to-Start; Finish-to-Finish; Start-to-Finish.
Assume the following activities for a project along with their estimated durations and predecessors. Describe how critical path analysis would be applied to this project, and calculate the critical path. Define the concepts: slack/float, expedite/crash, and fast tracking and explain what their implications are for this project?
Calculate Possible Activity paths
Identify critical path
Activity
|
Estimated Duration in Days
|
Predecessor
|
A
|
2
|
None
|
B
|
4
|
A
|
C
|
3
|
A
|
D
|
1
|
C,B
|
E
|
1
|
C,D
|
F
|
3
|
D,E
|
G
|
2
|
F
|
What are the seven IT project risk management processes?
What is a risk response plan? What should be included?
Compare the three types of project risk: known, known-unknown, and unknown-unknown. Give an example (not discussed in the text book) of each. Describe the qualities of a good project metric.
What are the key differences (4-5) between the Agile Project Management approach and Waterfall (Traditional Project Management)