Using the table below, which activity is on the critical path?
|
Activity
|
Immediate Predecessor(s)
|
Most
Optimistic
|
Most
Likely
|
Most
Pessimistic
|
A
|
---
|
2
|
4
|
6
|
B
|
---
|
1
|
4
|
7
|
C
|
A
|
2
|
2
|
2
|
D
|
B
|
1
|
7
|
10
|
E
|
D
|
2
|
4
|
6
|
F
|
E
|
1
|
2
|
3
|
G
|
C
|
3
|
4
|
17
|
H
|
D,G
|
3
|
7
|
11
|
I
|
D
|
8
|
9
|
10
|
J
|
F,H
|
4
|
5
|
6
|
K
|
I
|
1
|
1
|
1
|
Additional Information
The given activity belongs to Operations Management and it is about finding the activity which is on the critical path from the given activities and their respective times.