Problem:
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in
- The lessons learned. What should the project manager do?
- Ask the sponsor to close the project and pay the contracted penalty.
- Check with the team to learn what can be done, and consult an expert.
- Check that this information was documented correctly. Meet with the sponsor to ask for their support.