Define given terms: Actual Cost of Work Performed (ACWP); Budgeted Cost of Work Performed (BCWP); Budgeted Cost of Work Scheduled (BCWS).
• ACWP is the amount of attempt (expressed as like or in monetary terms) which has been expended in acquiring to a particular point into a project.
• BCWP is the amount of effort or cost which must have been expended within acquiring to a particular point.
• BCWS is the amount of effort or cost which must have been expended at an exact point in the project.