Problem: TheBestEver company produces three types of trucks: small, mid, and heavy. The production of any type of truck requires three install operations. The following table shows the time required for each operation 11 minutes.
|
Small |
Medium |
Heavy |
Stamping |
4 |
5 |
6 |
Motor Install |
8 |
12 |
15 |
Wiring |
10 |
15 |
20 |
The time needs for stamping i1s 30 minutes per hour. The time available for motor installation 1s 60 minutes per hour. The company has two stations for wiring and each of them 1s available for 45 minutes per hour. The profit made 1s $20 from each Small Truck, $30 from each Medium Truck, and $40 from each Heavy Truck.
a. Define decision variables. Your definition must include unit size & time frame.
b. Develop the Objective Function.
c. Find the constraints.