Debited to construction expenditure


In late June, the Everest Construction Co. submitted a progress billing on a construction contract for $500,000. On July 2, the bill was approved for payment, subject to a five percent retention, as provided by the contract. The amount that should be debited to Construction Expenditure is:

A) $475,000.

B) $497,500.

C) $500,000.

D) $ 25,000.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Debited to construction expenditure
Reference No:- TGS092980

Expected delivery within 24 Hours