Data for the Darth Vader Manufacturing Company for the month of July 2005 are as follows:
Beginning work in process - 1,600 units
Direct materials (100% complete): $42,000
Conversion (70% complete): $9,000
Operations for the month of July:
34,000 units started
Direct materials: $1,309,000
Conversion: $706,920
Ending work in process - 4,000 units
Direct materials were 100% complete
Conversion was 60% complete
Prepare a process costing analysis for the month of July.