cutting area capacity - glass companywhat if


Cutting Area Capacity - Glass Company

What if cutting area capacity is increased?

ince this process starts the whole production process it makes one think what if i start with initial surplus capacity, will overall production increase? Well it depends but in present case it won't since as described and explained above the bottleneck is process of shaping & edging, it's set up as well as process time and if something has to be done for capacity it is this place and not cutting area since doubling cutting process will lead to nothing but surplus WIP at the mouth of shaping & edging.