Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $8,400, direct labor of $4,100, and applied overhead of $3,485. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on account) for $30,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry incurs the following costs during July.