1. Current good practice in assessing the capabilities of teams and organizations contains a strong element of self-assessment.
a. true b. false
2. If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance? a. -$300 b. -$100 c. $100 d. $300
3. On well-managed programs, the operations and maintenance phase of the program life cycle usually:
a. is a large portion of the total effort b. is a small portion of the total effort c. entails heavy design work d. entails heavy development work
4. . On major programs, it makes sense for both buyer and contractor to maintain CCBs.
a. true b. false