Critical ratio scheduling rule


Assignment:

The following jobs are waiting to be processed at Jeremy LaMontagne’s machine center. Today is day 250.

Job Date job Received Production days needed Date job due
A 215 30 260
B 220 20 290
C 225 40 300
D 240 50 320
E 250 20 340

Using the critical ratio scheduling rule, in what sequence would the jobs be processed.

Provide complete and step by step solution for the question and show calculations and use formulas.