Assignment:
The following jobs are waiting to be processed at Jeremy LaMontagne’s machine center. Today is day 250.
Job |
Date job Received |
Production days needed |
Date job due |
A |
215 |
30 |
260 |
B |
220 |
20 |
290 |
C |
225 |
40 |
300 |
D |
240 |
50 |
320 |
E |
250 |
20 |
340 |
Using the critical ratio scheduling rule, in what sequence would the jobs be processed.
Provide complete and step by step solution for the question and show calculations and use formulas.