The following jobs are waiting to be processed at Jeremy LaMontagne’s machine center. Today is day 250.
     
| Job | Date job Received | Production days needed | Date job due | 
| A | 215 | 30 | 260 | 
| B | 220 | 20 | 290 | 
| C | 225 | 40 | 300 | 
| D | 240 | 50 | 320 | 
| E | 250 | 20 | 340 | 
Using the critical ratio scheduling rule, in what sequence would the jobs be processed.
Provide complete and step by step solution for the question and show calculations and use formulas.