Consider a project which consists of six activities. The precedence relationships and activity times are as follows:
Activity
|
Preceding Activities
|
Time (Days)
|
1
|
|
16
|
2
|
|
30
|
3
|
1
|
15
|
4
|
2
|
5
|
5
|
1
|
5
|
6
|
3, 4
|
5
|
What is the critical path for completion of the project?
A. 1 → 3 → 6
B. 2 → 3 → 5
C. 2 → 4 → 6
D. 1 → 2 → 4 → 6
Additional Requirement
This question belongs to Operations Management and it describes about the critical path for completing a project.