Critical path-project time


Problem:

Activity Immediate Predecessor Time (WEEKS)
A    -- 1
B A    4
C A 3
D B 2
E C,D    5
F D 2
G F 2
H E,G 3

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?