Critical path-pert calculation


Question: A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day ________ (rounded to nearest day).

a) 833
b) 807
c) 1009
d) 689
e) 631

Explain in one sentence why please.