Critical path and expected completion time of the project


Question 1: The information in the table shown below is available for a large fund-raising project.

a) Find out the critical path and the expected completion time of the project.

b) Plot the total project cost, starting from day 1 to the expected completion date of the project, supposing the earliest start times for each activity. Compare that result to a similar plot for the latest start times. What implication does the time differential have for the cash flows and project scheduling?

1820_large fund raising project.jpg

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Critical path and expected completion time of the project
Reference No:- TGS01727

Expected delivery within 24 Hours