--%>

Critical path activities and their time


Below is a table of activities required to finish a project:


Activity

Optimistic

Most Likely

Pessimistic

1

19

20

26

2

4

5

6

3

6

6

6

4

3

9

10


In calculating activity times for the project, which one of the following statements is correct?

A. Activity 1 will have the lowest variance

B. Activity 2 will have a variance of 0.11

C. Activity 3 will have the highest variance

D. Activity 4 will have a variance of 0.361

Additional Requirement

In here this question belongs to the operations management and it defines about the activities and their variance in time estimate.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Critical path activities and their time
Reference No:- TGS01104977

Expected delivery within 24 Hours