Complete the following:
Assignment 1:
Exercise consists of creating a project plan for a future project. Working in Microsoft Project, you will create a task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, and set up some resources. Think of a project you have in the future or a project you would consider undertaking. Set a start date for your project of June 1, 2017. Create at least 15 tasks, including the duration, and any predecessors that make logical sense in the progression of the project. The project must include at least 2 summary tasks with the rest as sub-tasks. Create and set up at least 5 resources, with at least one resource per type (work, material, and cost). Assign these resources to tasks to appropriate tasks in your project
Assignment 2:
Eercise consists of a list of tasks for a home yard project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors. Set a start date for your project of May 11th, 2018. In Manually Scheduled mode, enter the following tasks, including the duration, where specified. Tasks with unspecified duration (and in bold) are summary tasks and the rest are sub-tasks. When completed, change all of the tasks to automatically scheduled. Save the file and then submit the file via Canvas.
ID Task List
1 Preparation
2 Get trash bags
3 Pick up trash
4 Get rake
|
Duration Predecessors
5 min
25 min 2
5 min
|
5 Do the work
|
|
|
6
|
Rake front lawn
|
20 min
|
3,4
|
7
|
Rake side yards
|
15 min
|
3,4
|
8
|
Rake back yard
|
30 min
|
3,4
|
9
|
Bag up leaves
|
35 min
|
6,7,8
|
10
|
Bring out hoses
|
5 min
|
9
|
11
|
Connect hoses
|
8 min
|
10
|
12
|
Bring out outdoor furniture
|
15 min
|
11
|
13 Clean up
|
|
|
9,10,11,12
|
14
|
Dispose of leaves and trash
|
25 min
|
|
15
|
Arrange outdoor furniture
|
10 min
|
14
|