Create work flow sequence specified in problem given below. Do not consider any of the scheduling information given below in work. You may utilize MSP or hand drawn sketch to illustrate this information.
NETWORK DATA
Activity Duration Predecessors
A 6 None
B 12 A
C 10 A
D 9 B,C
E 15 B,C
F 11 B,C
G 3 D
H 8 D
I 10 F
J 6 G
K 5 E,F,H
L 10 I,J,K