The following table shows the allocation of work assignments and resources needed for an investment firm to make a decision on investing in company XYZ.
|
Task A
|
Task B
|
Task C
|
Profolio Managers
|
Week 1(S)
|
-
|
Week3(P)
|
Associates
|
-
|
Week 1(P)
|
Week2(S)
|
Analysts
|
Week 1(P)
|
Week 2(P)
|
Week2(S)
|
(P)=Primary (S)=Secondary
ResourceSpeadsheet
Resource
|
Week1
|
Week2
|
Week3
|
ProfolioManager
|
1
|
|
1
|
Associate
|
1
|
2
|
|
Analyst
|
2
|
5
|
|
Note:figuresinspreadsheetareperson-weeksofeffort
1. Create Responsibility Matrix.
2. Create Resource Gantt Chart.
3. Create Resources Loading Chart.