Question 1:
Illustrate and discuss the risk as per the Public Private Partnership Guidance Manual.
Question 2:
What are the most important objectives of transferring risks from the contracting authority to a private sector contractor?
Question 3:
Risk assessment is required to enable the objectives of risk transfer to be achieved. What are the purposes of assessing risk in a PPP project?
Question 4:
There are dissimilar categories of risk associated with infrastructure projects. List and describe the risks.
Question 5:
Describe the cost benefit analysis as employed to appraise large public sector investments.
Question 6:
Compare and contrast cost benefit analysis with the investment appraisal.
Question 7:
What are the complexities which occur in cost- benefit analyses which aren’t apparent in ordinary investment projects?